    Rated speed on the nameplate is not what a line makes in a week. Enter your lines and see what they can actually run after changeovers and real efficiency, and what a frozen schedule window would give back.

    The three lines below are example numbers for a mid-size food plant. Change them to yours. Everything runs in your browser and nothing is sent anywhere.

    Weekly demand

    12,950

    Realistic capacity

    12,793

    vs 19,200 rated (67%)

    Gap

    157 short

    Tightest line

    Filling line 1

    109% loaded

    +854 units a week come back if the schedule is frozen and the unplanned changeovers stop. That is 7% more output from the same lines, with no new equipment and no extra shifts.

    Rated
    9,600
    Realistic
    5,875
    Demand
    6,400
    109% loaded

    525 units short (about 6.1 more run hours a week)

    Changeovers take 12 of 80 scheduled hours. Realistic output is 61% of the rated figure.

    Rated
    7,200
    Realistic
    5,142
    Demand
    4,900
    95% loaded

    242 units of room a week

    Changeovers take 7 of 80 scheduled hours. Realistic output is 71% of the rated figure.

    Rated
    2,400
    Realistic
    1,776
    Demand
    1,650
    93% loaded

    126 units of room a week

    Changeovers take 3 of 40 scheduled hours. Realistic output is 74% of the rated figure.

    Want these results in your inbox?

    We'll send your results and one note on where your schedule is most likely to break. No newsletter.

    What this is worth to you

    $111,291

    a year, plus a one-time cash release

    Recovered margin a year$87,091
    Carrying cost saved a year$24,200
    One-time cash freed$110,000

    Estimates from the numbers on this page. Rough figures are fine.

    How the numbers work

    • Scheduled hours = hours per shift × shifts per day × days per week.
    • Changeover hours = (planned + unplanned changeovers) × hours per changeover.
    • Run hours = scheduled hours minus changeover hours, never below zero.
    • Rated output = rated units per hour × scheduled hours.
    • Realistic output = rated units per hour × run hours × running efficiency.
    • Frozen-window output = the same, counting only the planned changeovers.
    • Loaded % = weekly demand ÷ realistic output.

    On packaging lines, 65 to 80% running efficiency is common.