Free tool

    Capacity Reality Check

    Rated speed on the nameplate is not what a line makes in a week. Enter your lines and see what they can actually run after changeovers and real efficiency, and what a frozen schedule window would give back.

    The three lines below are example numbers for a mid-size food plant. Change them to yours. Everything runs in your browser and nothing is sent anywhere.

    Weekly demand

    12,950

    Realistic capacity

    12,793

    vs 19,200 rated (67%)

    Gap

    157 short

    Tightest line

    Filling line 1

    109% loaded

    +854 units a week come back if the schedule is frozen and the unplanned changeovers stop. That is 7% more output from the same lines, with no new equipment and no extra shifts.

    Rated
    9,600
    Realistic
    5,875
    Demand
    6,400
    109% loaded

    525 units short (about 6.1 more run hours a week)

    Changeovers take 12 of 80 scheduled hours. Realistic output is 61% of the rated figure.

    Rated
    7,200
    Realistic
    5,142
    Demand
    4,900
    95% loaded

    242 units of room a week

    Changeovers take 7 of 80 scheduled hours. Realistic output is 71% of the rated figure.

    Rated
    2,400
    Realistic
    1,776
    Demand
    1,650
    93% loaded

    126 units of room a week

    Changeovers take 3 of 40 scheduled hours. Realistic output is 74% of the rated figure.

    What this is worth to you

    $111,291

    a year, plus a one-time cash release

    Recovered margin a year$87,091
    Carrying cost saved a year$24,200
    One-time cash freed$110,000

    Estimates from the numbers on this page. Rough figures are fine.

    How the numbers work

    • Scheduled hours = hours per shift × shifts per day × days per week.
    • Changeover hours = (planned + unplanned changeovers) × hours per changeover.
    • Run hours = scheduled hours minus changeover hours, never below zero.
    • Rated output = rated units per hour × scheduled hours.
    • Realistic output = rated units per hour × run hours × running efficiency.
    • Frozen-window output = the same, counting only the planned changeovers.
    • Loaded % = weekly demand ÷ realistic output.

    On packaging lines, 65 to 80% running efficiency is common.

    Want this on your real orders instead of estimates? Send a few Excel files, your open orders and line hours, with customer names blanked if you like, and we will show you the result in days.

    Book a planning walkthrough